|
|
7.1 Introduction
This chapter provides more examples of typical mitigation techniques and options. Information provided is not to be considered all-inclusive, nor is it intended to limit the ingenuity or resourcefulness of designers, contractors, and inspectors, or create a strategy uniquely suited to the characteristics of a specific project.
| The level of detail in a contract required to address construction noise mitigation is dependant on the complexity of the project, the amount and type of work required, and the sensitivity of the area beyond the project boundary. Therefore, not all projects require the same amount of detail. Such detail could range anywhere from the inclusion of a standard specification requiring the contractor to be governed by local noise ordinances, to realigning the highway, providing for abatement structures, and/or relocation of residents. The effective control of highway construction noise can be achieved in much the same manner as the control of operational traffic by considering the following techniques:
• Mitigation at the source; • Mitigation along the path; and • Mitigation at the receiver. Public involvement and project coordination are also an essential components of the overall mitigation strategy worthy of consideration during all phases of a project. For a more detailed discussion of this topic, refer to Chapter 8. Most of the options presented in this chapter can be employed independently or in combination, depending on the scope of the project and the resultant effects that are desired. While reductions in noise levels will vary with the method employed, consideration of all practical and feasible options is essential during all stages of the project development from planning, through design and construction, to final evaluation. |
Table 7.1. Overview of mitigation options.
|
7.2 Design Options
Noise impacts can occur on any project involving the construction of a highway facility. While the magnitude of the impact construction noise may have on a community may not be known early in the project development stages, measures can be implemented during the design phase that can help to reduce the anticipated noise impacts at sensitive receptors. However, design changes and modification to project layout are not always practical or feasible. Also, the magnitude of the noise reduction attained from some of these techniques is usually difficult to determine prior to and possibly even during construction.
7.2.1 Design Phases.
In addressing construction noise mitigation during the design phases of a project, abatement opportunities can be considered for a variety of areas and features including those listed below:
• Storage Areas: During the planning and design stages of a project, storage areas may be able to be designated in locations removed from sensitive receptors. Where this is not possible, the storage of waste materials, earth, and other supplies may be able to be positioned in a manner that will function as a noise barrier.
![]() |
| Figure 7.1. Storage area in highway right-of-way. (Photo #177) |
![]() |
![]() |
| Figure 7.2. Partial shielding of storage area in residential area. (Photo #247) |
Figure 7.3. Storage area in remote location. (Photo #1257) |
![]() |
| Figure 7.4. Designated haul routes. (Photo #560) |
![]() |
| Figure 7.5. Shifting of traffic to accommodate construction. (Photo #1261) |
![]() |
| Figure 7.6. Existing retaining wall acting as noise barrier during construction. (Photo #543) |
7.2.2. Sequence of Operation.
The sequencing and scheduling of construction operations is equally important in addressing and mitigating construction-related noise
• Concurrent Operations: It may be possible to schedule several noisy operations concurrently to take advantage of the fact the combined noise levels produced may not be significantly greater than the level produced if the operations were performed separately.
• Early Construction of Noise Barriers: Ultimately, noise barriers that are to be constructed as part of the project for traffic noise abatement can possibly be installed during the initial stages of construction to reduce the noise impacts of the construction.
![]() |
| Figure 7.7. Early construction of noise barriers. (Photo #447) |
7.2.3 Alternative Construction Methods.
Alternatives to standard construction techniques may also be available and determined to be more practical and/or cost-effective in dealing with construction noise impacts and perceptions. Examples associated with several operations are discussed below.
• Pile Driving: Pile driving may produce noise levels in excess of acceptable limits, even when feasible noise reduction methods are used. Various dampening and shielding methods discussed later can attain some reduction. However, such methods rarely reduce the noise level to an acceptable level for the sensitive receptors close to the site. As an alternative to driving piles, it is possible to use vibration or hydraulic insertion techniques. Drilled or augured holes for cast-in-place piles are another alternative that may produce noise levels significantly lower than the traditional driving method.
![]() |
| Figure 7.8. Alternative to pile driving. (Photo #509) |
![]() |
| Figure 7.9. Diesel compressor with baffled housing. (Photo #69) |
7.3 Contract Specifications and Special Provisions
Contract specifications and special provisions are typically produced during the design stages of project development and may be included in the project plans and contract documents. Ideally, use of these documents is considered in conjunction with other control methods to achieve an overall construction noise strategy. Examples of such specifications ref. 023, ref. 028, ref. 103, and ref. 053 are referenced in this Handbook.
7.3.1 Construction Noise Criteria Limits.
When establishing suitable noise criteria limits for specifications and special provisions, they can be characterized as either being “relative” or “absolute” or a combination both. These can be defined even further by dividing the set limits into specific time periods during the day such as daytime, evening and nighttime. Experience has shown that the “absolute” criteria combined with the “relative” criteria levels appears to be more realistic and tends to be self-adjusting to varying conditions, particularly when defined for the various periods of the day. An example of one such set of construction noise criteria is shown in Table 7.1.
| Table 7.2. Example of Absolute and Relative Construction Noise Criteria Limits |
| Lot-Line Construction Noise Criteria Limits A-weighted in dB, RMS slow | Noise Receptor Locations and Land-Uses | Daytime (7 AM - 6 PM) |
Evening (6 PM - 10 PM) |
Nighttime (10 PM - 7 AM) |
|||||
| L10 | Lmax | L10 | Lmax | L10 | Lmax | Noise Sensitive Locations: Residences, Institutions, Hotels, etc. | 75 or Baseline + 5 (whichever is louder) | 85 90 (impact) |
Baseline + 5 | 85 | Baseline +5 (if Baseline <70) Baseline +3 (if Baseline >70) |
80 |
| Commercial Areas: Businesses, Offices, Stores, etc. | 80 or Baseline + 5 (whichever is louder) | None | None | None | None | None | |||
| Industrial Areas Areas: Factories, Plants, etc. | 85 or Baseline + 5 (whichever is louder) | None | None | None | None | None | |||
| L10 noise compliance readings are averaged over 20 minute intervals. Lmax noise compliance readings can occur instantaneously. Baseline noise conditions must be measured and established prior to construction work, commencing in accordance with the noise specification, which requires baseline noise readings over three 24-hour periods at each receptor lot-line location. | |||||||||
| Source: Adapted from Central Artery/Tunnel Noise Specification and Table 2 in Appendix A. | |||||||||
| Table 7.3. Example of Possible Construction Equipment Noise Emission Criteria Limits |
| Equipment Description | Lmax Noise Limit at 50 feet, dB, slow | ||||||||
| All other equipment > 5 HP | 85 | ||||||||
| Auger Drill Rig | 85 | ||||||||
| Backhoe | 80 | ||||||||
| Bar Bender | 80 | ||||||||
| Blasting | 94 | ||||||||
| Boring Jack Power Unit | 80 | ||||||||
| Chain Saw | 85 | Clam Shovel | 93 | Compactor (ground) | 80 | Compressor (air) | 80 | Concrete Batch Plant | 83 | Concrete Mixer Truck | 85 | Concrete Pump | 82 | Concrete Saw | 90 | Crane (mobile or stationary) | 85 | Dozer | 85 | Dump Truck | 84 | Excavator | 85 | Flat Bed Truck | 84 | Front End Loader | 80 | Generator (25 KVA or less) | 70 | Generator (more than 25 KVA) | 82 | Gradall | 85 | Grader | 85 | Horizontal Boring Hydraulic Jack | 80 | Hydra Break Ram | 90 | Impact Pile Driver (diesel or drop) | 95 | Insitu Soil Sampling Rig | 84 | Jackhammer | 85 | Mounted Impact Hammer (hoe ram) | 90 | Paver | 85 | Pickup Truck | 55 | Chain Saw | 85 | Pneumatic Tools | 85 | Pumps | 77 | Rock Drill | 85 | Scraper | 85 | Slurry Plant | 77 | Slurry Trenching Machine | 82 | Soil Mix Drill Rig | 80 | Tractor | 84 | Vacuum Street Sweeper | 80 | Vibratory Concrete Mixer | 80 | Vibratory Pile Driver | 95 | Welder | 73 |
| Source: Adapted from Central Artery/Tunnel Noise Specification. | |||||||||
7.3.2 Time Periods and Duration.
Time constraints and use of equipment regulations can be very effective in reducing the impacts caused during sensitive time periods. In addition, operating noisy equipment only when necessary and switching off such equipment when not in use can minimize noise impacts.
![]() |
| Figure 7.10. Nighttime bridge construction. (Photo #661) |
![]() |
| Figure 7.11. Nighttime demolition operation. (Photo #1049) |
7.3.3 Specified Equipment.
Another effective noise mitigation technique involves use of the quietest practical type of equipment. To avoid confusion and misinterpretations, such types should be specified in the contract specifications and special provisions.
7.3.4 Noise Related Incentives/Disincentives.
Another technique worthy of consideration involves the inclusion of incentives and/or disincentives in the contract specifications to encourage the contractors to participate in the mitigation program and to make them more accountable for impacts.
7.3.5 Training Programs for Contractors.
It may be appropriate to require contractors to participate in training programs related to project-specific noise requirements, specifications, and/or equipment operations. Such training may be provided by agency or project management personnel, outside consultants, and/or equipment manufacturers or suppliers. For example, project personnel (or consultants assigned to the project) may train the contractor on the measurement of construction-related noise levels that may be required to meet the contract specifications.
The contractor may also receive on-site training related to the noise-specific issues and noise-critical areas and sites adjacent to the project. Equipment manufacturers and/or suppliers may be available to provide training to the contractor concerning the proper use of the noise abatement features of specific pieces of their construction equipment. Any training requirements that are envisioned to be required would typically be described or referenced within the contract’s specifications and special provisions.
7.4 Mitigation at the Source
Source control is, in general, the most effective form of noise mitigation and involves controlling a noise source before it is able to emit potentially offensive noise levels. Construction noise (exclusive of blasting) is typically generated by two source types.
7.4.1 Equipment – All Types.
The following discussions relate to both stationary and mobile construction equipment:.
![]() |
![]() |
| Figure 7.12. In some instances, using a less noisy piece of equipment (right) may be possible, as opposed to using more conventional and sometimes noisier equipment (left) to perform the same operation. (Photos #505 and #506) |
|
![]() |
| Figure 7.13. Muffler system on recycling equipment. (Photo #1287) |
![]() |
![]() |
| Figure 7.14. Unshielded, non-baffled equipment. (Photo #74) |
Figure 7.15. Shielded compressor. (Photo #18) |
![]() |
![]() |
![]() |
|
| Figure 7.16. Examples of pile driver shielding and dampening. (Photos #1277, #1281, and #1308) |
|
![]() |
| Figure 7.17. Bubble curtain. (Photo #57) |
![]() |
![]() |
| Figure 7.18. Bubble curtain air release ring. (Photo #51) |
Figure 7.19. Bubble curtain. (Photo #52) |
![]() |
| Figure 7.20. Straw bail enclosure for stationary equipment. (Photo #58) |
![]() |
![]() |
| Figure 7.21. Blasting mats constructed with black tires (in foreground of photo. (Photo #261) |
Figure 7.22. Blasting mats being placed into position. (Photo #1341) |
![]() |
| Figure 7.23. Older equipment may be as efficient as new, but may not meet noise emission requirements. (Photo #809) |
![]() |
| Figure 7.24. Newer paving equipment. (Photo #813) |
![]() |
| Figure 7.25. Regular service of equipment is an essential component to quietest operation possible. Equipment suppliers may also be valuable sources of training related to proper use of equipment. (Photo #827) |
7.4.2 Stationary Equipment.
Whenever possible, positioning stationary noise sources such as generators and compressors as far away as possible from noise sensitive areas should be considered. Temporary barriers can be employed and/or enclosures can be built around noisy equipment. These techniques can significantly reduce noise levels and, in many cases, are relatively inexpensive. These barriers can typically be constructed on the work site from common construction building material (plywood, block, stacks, or spoils). Enclosures are often constructed from commercial panels lined with sound absorbing material to achieve the maximum possible shielding effect.
![]() |
| Figure 7.26. Temporary shielding of stationary equipment. (Photo #1340) |
![]() |
| Figure 7.27. Temporary barrier around stationary activity. (Photo #1339) |
7.4.3 Mobile Equipment.
Many construction operations are mobile and tend to progress along the length of a project at varying rates. Noise levels at the receiver tend to vary considerably, not only as the speed and power of the equipment varies, but also as the equipment is constantly changing in terms of its distance to the receivers and its relative location. To address this, all the equipment noise mitigation techniques listed in Section 7.4.1 are worthy of consideration with the exception of the enclosures. Enclosing mobile equipment is usually not possible, unless the operation is slow moving and the enclosures can be easily moved.
7.5 Mitigation along the Path
In some situations, such as in urban areas or on isolated sections of a project, it may be beneficial and necessary to construct barriers adjacent to the work area or at the right-of-way. These can take the form of natural shielding, temporary shielding, and/or permanent shielding.
7.5.1 Existing Features.
Utilizing existing shielding such as berms, existing noise barriers, or structures for relatively static equipment such as pumps, generators, compressors, air ventilation, batch plants, and storage areas may be appropriate.
![]() |
| Figure 7.28. Existing noise barrier left in place until replacement noise barrier is constructed. (Photo #483) |
![]() |
| Figure 7.29. Equipment and storage area shielded by existing structures. (Photo #558) |
7.5.2 Temporary Abatement.
Advantage may also be taken of the screening effect of any nearby object such as parapet walls, buildings, trailers, or temporary site offices.
![]() |
![]() |
![]() |
![]() |
| Figure 7.30. Use of existing structure and temporary plywood on chain link fence plus absorptive mats to shield recycling equipment. (Photos #690, #390, #395, and #679) |
|
![]() |
| Figure 7.31. Temporary barrier of plastic material. (Photo #194) |
![]() |
![]() |
| Figure 7.32. Storage trailers modified to act as temporary noise barrier. (Photos #1030 and #1029) |
|
7.5.3 Early Construction of Permanent Noise Barriers.
As mentioned in Section 7.2.2, shielding of certain construction activities may be accomplished by specifying that the construction of permanent noise barriers be implemented as early as possible during the project’s construction phase. Obviously, some noise-producing activities will likely be required before such barriers can be constructed. In addition, the actual erection of the noise barriers is a noise generating activity.
![]() |
| Figure 7.33. Early construction of permanent noise barriers. (Photo #472) |
7.6 Mitigation at the Receiver
Mitigation at a receiver can be vary in its complexity, ranging anywhere from relocating residents for a day to insulation of a building. Even after mitigation measures have been applied, the outcome may still be unpredictable with no guarantees that the implemented methods achieve expected results. Therefore, mitigation at the receiver should only be considered as a last alternative. However, there are cases where creative techniques have been successfully implemented.
7.6.1 Building Envelope Improvements.
Building envelope mitigation techniques to reduce construction noise can include items such as sealing existing building elements, providing new sealed windows and doors, adding building insulation, etc. Such techniques, while effective, may also require modification of the building’s heating, ventilation, and air conditioning system. Prior to proposing such treatments, thorough consideration of the costs and implications of such modifications is strongly suggested.
![]() |
![]() |
![]() |
|
| Figure 7.34. Installation of a complete air handling system and window treatments at urban school solely to abate construction noise due to future conversion of arterial to depressed expressway. (Photos #1300, #1303, and #1304) |
|
7.6.2 Noise Masking.
Noise masking is a technique that is still in the developmental stage, but may have potential in isolated cases. Masking considerations could include techniques such as constructing water falls or other cascading water designs, employment of noise cancellation technologies, changing “background” noise levels, etc. Such techniques require the consideration of the type of noise generator (stationary, mobile, etc.), the source’s noise frequency content, variability of the noise source in terms of its magnitude and duration, and the noise environment of the receptor being protected.
![]() |
![]() |
| Figure 7.35. Experimental sound system used to mask nighttime construction noise in the community. (Photos #42 and #38) |
|
7.6.3 Relocation of Residents.
In certain instances it may be appropriate, and possibly more cost-effective, to temporarily relocate a resident or residents from the construction area. By temporarily eliminating the noise receptor, noisy construction activities may be able to be undertaken unimpeded and completed in far less time than would be required under a noise-restrictive procedure. Such a technique was employed when several spans of a damaged interstate highway structure required demolition in close proximity to a row of residences. The residents were relocated to a hotel for a weekend while the damaged bridge structure was completely demolished. Another project which included relocation of residents as a mitigation measure is discussed in Reference 103.
7.7 Selection of Mitigation Measures
After the potential impacts resulting from the construction activities have been established, the next step in the process is the selection of appropriate control measures to be implemented on the project. This can typically be accomplished by identifying all feasible measures that could be used, selecting the most suitable techniques, and assembling them into a final mitigation strategy.
7.7.1 Identification of Feasible and Reasonable Measures.
This stage involves identification of control strategies which could be implemented to bring about the desired reductions in noise impacts. Some of the factors that influence this identification process are:
7.7.2 Selection of Mitigation Strategies.
This stage involves the selection of a reasonable control strategy from the methods examined in the identification stage. The measure or measures chosen should be weighed as to their benefits compared to their adverse effects. This weighting should take into consideration:
7.8 Monitoring Noise Levels During Construction
Regardless of the types of noise abatement strategies and techniques employed on any particular project, successes or failures are ultimately determined by resultant effects on noise levels at sensitive sites and the adherence of the resultant noise levels to the stated construction noise level criteria.
Evaluation of such success or failure is typically addressed by a program, the requirements of which are usually detailed in the contract specifications and special provisions. An adequate program requires:
7.9 Examples of Construction Noise Regulations
While 23 CFR 772 requires the evaluation of construction noise and the consideration of mitigation for identified construction noise impacts, it does not include specifications or specific language related to construction noise mitigation techniques, criteria, or restrictions. Such detail is included in various State and local documents, some of which are included as References 001, 009, 053, 077, and 103 and/or referred to in Table 10.1 of this Handbook.
< previous | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | a | b | c | next >